For architects, MEP engineers and quantity surveyors
Specify lightning protection, earthing and surge protection with confidence.
Free design input at concept and tender stage: risk assessments, layouts, specification clauses and BOQ items, from a contractor that installs and maintains these systems across Rwanda.
What we provide
Support at every project stage.
Concept and design
IEC 62305-2 risk assessment to set the protection level, ESE or conventional approach, and coordination with the structure and roof.
Drawings and details
Air-termination layout, protection radius, down-conductor routes, earthing layout, test points and SPD locations in the distribution boards.
Specification and BOQ
Specification clauses and BOQ line items your QS can price, with datasheets and test reports for the products proposed.
Tender clarifications
Technical answers during tender evaluation, and help checking that bids meet the standards specified.
Site coordination
Embedded earthing and down-conductor provisions agreed with the main contractor before concrete and roofing.
Handover documents
As-built drawings, earth resistance records and an inspection schedule for the facility manager.
Comparing bids? Read how to evaluate lightning protection bids, or run the risk assessment tool for a first protection level and bill of materials.
CAD and BIM
Details and datasheets.
CAD details and datasheets on request
Typical details (air terminal and mast fixing, down conductor and test joint, earth pit, SPD board layout) in DWG or PDF, and product datasheets with test reports, are sent by email. Use the form below and tell us the format you need.
Specification text
Clauses you can adapt for your project.
Replace the values in [square brackets] with your project's values. These clauses are a starting point; the project engineer remains responsible for the final specification.
1. Lightning risk assessment
A lightning risk assessment shall be carried out for each structure in accordance with IEC 62305-2, taking into account the local ground flash density, structure dimensions, location, occupancy, contents and incoming services. The assessment shall determine whether protection is required and the required Lightning Protection Level (LPL). The calculation shall be submitted for approval before detailed design.
2. External protection: ESE system
The external lightning protection system shall use early streamer emission (ESE) air terminal(s) designed and installed in accordance with NF C 17-102 (2011) for Protection Level [I/II/III/IV]. Each ESE terminal shall have an efficiency (ΔT) declared by the manufacturer and verified by an independent laboratory test report to NF C 17-102 Annex C, to be submitted with the bid. The terminal shall be mounted at least 2 m above the highest point of the area to be protected, on a mast of [height] m. The protection radius shall cover the whole structure for the stated level. Each ESE terminal shall have at least two down conductors where required by NF C 17-102.
3. External protection: conventional system
Where a conventional system is specified, the air-termination system (rods, catenary wires and/or mesh conductors) shall be designed in accordance with IEC 62305-3 for Lightning Protection Level [I/II/III/IV], using the rolling sphere, protective angle or mesh method as appropriate. Mesh size, down-conductor spacing and separation distances shall comply with IEC 62305-3 for the stated level. Components shall comply with the IEC 62561 series.
4. Down conductors and test joints
Down conductors shall be [tinned copper tape 25 × 3 mm / 50 mm² minimum cross-section], routed by the shortest and most direct path to earth, avoiding sharp bends, and fixed at intervals not exceeding 1 m. Each down conductor shall have a disconnecting test joint at approximately 2 m above ground and mechanical protection up to that height. A lightning strike counter shall be installed on [the main down conductor of each ESE terminal].
5. Earthing
Each down conductor shall terminate in an earth termination system of [copper-bonded earth rods / a triangle of three rods / a ring earth electrode], with all joints made by exothermic welding and each electrode accessible through an inspection pit. The earth resistance of each earth termination, measured with the test joint open, shall not exceed 10 Ω. Where soil conditions prevent this, additional electrodes or conductive compound shall be used. All lightning protection earths shall be bonded to the main earthing terminal of the building.
6. Surge protection
Surge protective devices (SPDs) shall be installed in accordance with IEC 62305-4 and IEC 60364-5-53, and shall comply with IEC 61643-11 (power) and IEC 61643-21 (telecom and signal). A Type 1 (or Type 1+2) SPD shall be installed at the main distribution board of any structure fitted with external lightning protection, with Type 2 SPDs at sub-distribution boards and Type 3 SPDs at sensitive equipment as required. Solar PV systems shall have DC SPDs to IEC 61643-31 at the inverter and, where the cable run exceeds 10 m, at the array. SPD connecting leads shall be kept as short as possible.
7. Testing, handover and inspection
On completion the contractor shall measure and record the earth resistance of each earth termination and the continuity of all conductors, and shall hand over as-built drawings, product datasheets, test reports and an inspection schedule in accordance with IEC 62305-3 Annex E. The contractor shall carry out [one] free inspection within [12] months of handover and shall quote for annual inspection thereafter.
Design support
Send us your drawings.
Tell us about the project and the stage it is at. An engineer will reply with a risk assessment, layout, specification review or BOQ input, as you need.
- Architects and interior designers
- MEP and electrical consultants
- Quantity surveyors and cost consultants
- Project managers and developers
Please contact us directly
This online form is not available at the moment. Call or WhatsApp +250 782 212 428, or email [email protected], and we will help you.